in either the Zynq 7Z010 or 7Z020 version.
7 weeks from Avnet?
in either the Zynq 7Z010 or 7Z020 version.
7 weeks from Avnet?
My experience is that an acceptable 3 week delay turns into an unacceptable 18 week delay *after* the order is placed and *confirmed*...
21st January 2014 stock list shows
1: microzed - 3 weeks lead time
2: jtag hs2 cable - in stock
which is acceptable, so order is placed
21st January receive email confirming those order details. Good.
23rd January check order status expected ship date 27 MAY - *18 weeks*, not 3 weeks. Not good.
Mid February microzed is in stock, expected ship date still 27 May.
Today microzed out of stock, still expect to ship 27 May. Will it arrive, if at all? Who knows.
I got Apr22 or sooner for 7Z020 and 20March for 7Z010 from my Avnet contact and I ordered them on Jan2.
Not sure what's going on. Demand so high or revision changes because of some problems or what? And as I understand this is the the same situation since release in Aug.
I checked with the internal Avnet group that handles getting the MicroZed built and put into stock. Demand has been high. We should have MicroZed 7Z010 and 7Z020 SOMs in stock within 2 weeks. The MicroZed 7Z010 'evaluation kit' could take as long as 4 weeks to show stock as the backlog is very high on that one.
-Gary
Based on my experiences (described above), don't order anything else with the MicroZed.
Let us know when you receive anything, please.
17 days later... now Avnet shows 10weeks lead time for both 7Z010 and 7Z020 :) You can only imagine what I have to do to keep my boss of my back. Hope if/when we are going to release project - problems with stock will be resolved.